Solar Battery Grants
Commercial

Peak shaving with a battery: how it works and how to calculate the saving

Peak shaving only pays if your bill charges for peaks or reserved capacity. Here is how the saving is calculated, with placeholder numbers, and what to check first.

  • Independent: not a government site, not an installer
  • Every rule checked against official sources
  • Free, no obligation, we reply by email

Planning commercial battery storage?

Tell us about the site and we reply by email.

Free to useNot an installerWe reply by email

Updated 8 October 2026. Independent guide; not a government website and not an installer.

Peak shaving means using a battery to supply part of a site's demand during its highest-demand periods, so the power drawn from the grid at those moments is lower. It only saves money if your electricity bill charges you for peaks or for reserved capacity, and how much it saves depends on your own half-hourly profile and tariff. This page explains what peak shaving and load shifting are, how a demand charge reduction is calculated, and what to check. The arithmetic below uses placeholder variables, not real tariffs, because rates differ by network area, voltage and supplier. It is written by an independent publisher, not an installer.

Peak shaving and load shifting in plain terms

Peak shaving trims the top off the demand curve. The battery discharges when site demand rises towards a set threshold, so the grid supplies only the amount up to that threshold. Load shifting moves energy use in time: the battery charges when electricity is cheaper or the site is quiet, and discharges when power is dearer or the site is busy. The two overlap and one controller can do both, but they save money on different lines of the bill.

Where the charge comes from

Larger business supplies are typically half-hourly metered. Their bills can include charges linked to the capacity you reserve on the network (your Maximum Import Capacity, sometimes called agreed supply capacity), and unit charges that differ by time of day. Supplier commentary in 2025 reported that capacity charges had risen sharply in several regions, which is one reason some sites now look closely at the capacity they hold and the peaks they hit. Your bill, your supplier and your network operator's published charging statement are the authority on what applies to you. Supplies on non-half-hourly meters may have no such charge, in which case there is nothing for a battery to shave.

A worked example with stated assumptions

Assumptions, not real figures. Every value below is a placeholder to show the method. Replace each with the figure from your own bill. This is not a forecast, a price or a promise of savings.

Define these variables from your own data:

  • P_before: the peak demand (kVA) your site hits in the period the charge is based on.
  • P_after: the peak you would hit if the battery covered everything above a set threshold.
  • R: the capacity or demand rate on your bill, in pence per kVA per day (or whichever unit your bill uses).
  • D: the number of days the charge applies in a year.

The annual saving on that charge is:

(P_before minus P_after) multiplied by R multiplied by D

As an illustration only, suppose P_before = 500 kVA, P_after = 400 kVA, R = 10 pence per kVA per day and D = 365 (all invented). The calculation is 100 kVA multiplied by 10 pence multiplied by 365 days, which is 365,000 pence, or £3,650 a year. Do not treat that as a typical result. It shows only that the saving scales with the size of the peak you remove and the rate you pay, and it falls to zero if your bill has no such charge.

What this simple calculation leaves out

  • The battery must be big enough for the peak. Shaving 100 kW off a peak that lasts three hours needs roughly 300 kWh of usable energy (kW multiplied by hours), before losses. A short sharp spike needs less energy but the same power rating.
  • The battery must be charged beforehand. If two high-demand days follow each other and the battery has not recharged, the peak comes back.
  • One miss can cost the saving. If the charge is set by the single highest half-hour in a period, a forecasting miss defeats the exercise. Ask how the controller handles this.
  • Round-trip losses mean you buy more electricity than you recover.
  • Capacity changes need paperwork. Lowering your agreed import capacity is a request to your network operator, and raising it later can be slow or costly. Do not reduce it on the strength of a battery that is not yet proven.
  • Charges change. Network charging methodologies are reviewed periodically, so a saving that depends on today's structure carries risk.

To get real numbers, ask your supplier or energy broker for your half-hourly data, usually available as a spreadsheet. Look at the shape of the peaks and check how the charge is calculated before asking any installer for a design. Our savings calculator is aimed at home batteries, so do not use it for a site with demand charges.

Planning a commercial battery project? Tell us about the site and we reply by email.Send an enquiry

When peak shaving is worth testing

  • Your site is half-hourly metered and a few short spikes (equipment start-up, EV chargers, process loads) set your peak.
  • The peak is short compared with the average load. A broad plateau is expensive to shave; a spike is cheaper.
  • You are approaching your agreed import capacity and an upgrade would be costly or slow.
  • You also have solar, so the same battery can do more than one job. See solar plus storage.

It is usually a weak case when demand is flat, when the peak lasts many hours, or when cheaper fixes exist, such as staggering equipment start-up or adjusting set points. Ask whether those were considered first.

Grid, planning and safety checks

The grid rules are the same as for any behind-the-meter battery. G98 stops at 16 A (3.68 kW) per phase, so a commercial battery usually needs G99. G99 Type A applies above that up to but not including 1 MW at a premises, with commissioning results due in an Installation Document within 28 days. Types B to D need at least 28 days' notice of the test scope, and the network operator may witness commissioning (ENA guide). Do not assume a battery that only discharges to your own site gets a lighter process: ask the network operator whether it still needs a G99 application. Ask whether the G99 wait could delay the saving and who is responsible for the application.

On planning, interior installs are generally not development, whereas an outdoor cabinet or container is operational development with no dedicated permitted development class for batteries. For 1 MWh and above, national guidance encourages early contact with the fire and rescue service. The commercial battery storage page has more on the checklist.

Funding reality

We could not find a live national grant for a commercial battery: the Industrial Energy Transformation Fund closed in July 2025 with no successor planned. The 0% VAT rate for home batteries does not apply to general commercial premises. Capital allowances are the main relief: the Annual Investment Allowance gives 100% relief up to £1m a year, but how a battery is classified for relief above that is not settled, so ask your accountant. See commercial battery funding.

Questions to ask an installer

  1. Which charge on my bill does this battery reduce, and which line of the bill shows it?
  2. Which half-hourly period did you analyse, and what peak did you assume could be cut?
  3. How does the controller predict peaks, and what happens if it misses one?
  4. What is the usable energy and the power rating, not just the headline capacity?
  5. How will my agreed capacity be handled with the network operator?
  6. What happens to the savings if network charges are restructured?

Common mistakes

  • Assuming every business bill has a demand or capacity charge.
  • Sizing by average load rather than by the peak shape.
  • Presenting a saving as certain when it depends on a tariff that can change.
  • Cutting import capacity before the battery has proven itself over a full billing cycle.

Frequently asked questions

What is peak shaving with a battery?

Peak shaving uses a battery to supply some of your demand during the highest-demand periods so the grid supplies less at those moments. It saves money only if your bill charges for peaks or for reserved capacity.

How do I calculate a peak shaving saving?

Multiply the peak reduction by the demand or capacity rate on your bill and by the number of days the charge applies. Take every input from your own bill and half-hourly data. The worked example on this page uses invented placeholder numbers to show the method only.

Does every business benefit from peak shaving?

No. If your meter is not half-hourly, or your bill has no capacity or time-of-day network charge, there may be nothing to save. A long flat plateau of demand is also costly to shave compared with a short spike.

What is the difference between peak shaving and load shifting?

Peak shaving caps the power you draw from the grid at the busiest moments. Load shifting moves when energy is bought, charging when power is cheaper and discharging when it is dearer. One battery can do both, but the savings come from different bill lines.

Do I need a G99 for a peak shaving battery?

Almost certainly. A commercial battery is normally above the G98 limit of 16 A (3.68 kW) per phase, so it goes through G99 with your network operator even if it never exports.

Sources and how we checked
Check your eligibility
Check eligibility