Short answer: batteries make most sense at charging sites where the available grid capacity is low compared with the power the chargers could draw, and where waiting for a bigger connection would take too long or cost too much. The battery recharges slowly from the existing connection and discharges quickly to chargers during busy periods. It is not always the cheapest answer: a larger connection, load management or fewer high-power chargers may do the job. This page is general education from an independent publisher; it is not engineering advice and quotes no prices.
Why charging sites run into grid limits
A rapid or ultra-rapid charger asks the network for a lot of power for short periods. A site with several of them can ask for far more than a typical commercial connection provides, and upgrading a connection can involve network reinforcement that the DNO controls. The ENA connection guide notes that reinforcement is usually non-contestable work, which only the DNO can carry out, and that offers can be queued where applications interact. That is why timelines and costs for bigger connections are hard to predict.
Where a battery fits in
A battery lets the site import steadily and deliver in bursts. Three other approaches are worth pricing alongside it:
- A larger connection. Often cleaner if the DNO can offer it on acceptable terms and dates.
- Load management. Software that shares available power between chargers so the site never exceeds its limit.
- A limited connection. Where the DNO agrees an import limit enforced by a control scheme; see our grid connection guide.
Sizing: the concepts, not the numbers
We give no sizing figures because they depend on the site. The questions that set the size are:
- Power versus energy. Power (kW) decides how many vehicles can charge at once. Energy (kWh) decides how long the battery can sustain it. A site with short, sharp peaks needs different proportions from one with long, steady demand.
- Gap to cover. The difference between the power the chargers could draw and what the connection supplies, and how often and for how long that gap occurs.
- Recharge window. The battery must refill from the connection between peaks; a site that is busy all day has little time to do that.
- Usage data. Real session data, or a credible forecast, beats a rule of thumb.
- Future growth. Adding chargers later changes everything, so ask how the design scales.
Connection route
A charging site is a demand connection, so the first conversation with the DNO is about import capacity. If the battery can export to the network, it is also generation and falls under G98 or G99; G98 covers up to 16 A (3.68 kW) per phase, above that you need G99 and an application before installing. NGED describes customer import and export limitation schemes under ENA Engineering Recommendation G100 as an option where the customer restricts net import or export rather than wait for reinforcement; the control scheme must hold the site to the agreed capacity, typically within 15 seconds, with settings locked against change without the DNO's written agreement. Expect to submit forms before installation and a completion form afterwards. Other DNOs have their own processes, so check yours. Ask the DNO in writing what it will offer and when, since we could not verify any single operator's timescale from a primary source.
Planning and fire safety
In England, an indoor battery that does not materially affect a building's external appearance is not development. Outdoor battery containers or cabinets are operational development, and the permitted development rights for renewables include no battery storage class, so planning permission or a lawful development certificate will usually be the route. Car parks and forecourts often have conditions already attached to their permissions, which is worth checking.
For systems of 1 MWh or more not associated with a dwelling, national planning guidance encourages applicants to engage the local fire and rescue service before applying. Below that size no such step is set out in that guidance, but it is still sensible to talk to your insurer, the fire service and building control early, particularly where batteries sit close to charging vehicles, customers or occupied buildings. Ask the supplier for the safety documentation and the detection and ventilation design for the specific product.
Cost and funding reality
Published UK per-kWh ranges for commercial batteries overlap because they come from different sources and system sizes (one 2026 industry article is listed below), and the battery is only part of an EV site's cost: chargers, civils, the connection and software all matter. We therefore quote no total. Compare itemised quotes and ask what happens to the cost if the DNO's offer changes.
On funding, the Local EV Infrastructure (LEVI) Fund on GOV.UK is aimed at local authorities in England, to provide charging for residents without off-street parking, mainly lower-power on-street charging. A private operator does not apply to it directly, and the GOV.UK page we read was an older version, so we could not confirm the scheme's current status. Do not plan a business case around grant funding you have not confirmed in writing. Other points: the 0% VAT rate for batteries covers homes and relevant charitable buildings, not general commercial premises; the Industrial Energy Transformation Fund closed in July 2025 with no successor; the Annual Investment Allowance covers up to £1m a year, and the tax class of a battery above that is unsettled, so ask your accountant. See commercial battery funding.
Questions to ask suppliers and your DNO
- What import capacity has the DNO offered, with what dates and conditions?
- Does the design rely on the battery exporting, or only on limiting import?
- Who applies for G99 or G100 approval and who carries the risk if refused?
- What happens to charger availability if the battery is offline?
- How is the battery warranted, monitored and maintained, and what does end-of-life cost?
- What would load management alone achieve at this site?
Common mistakes
- Sizing from a headline charger rating instead of real demand.
- Ordering before the connection terms are agreed.
- Assuming a battery removes the need for a DNO application.
- Treating grant schemes for on-street charging as open to private hubs.
- Leaving fire and insurance questions to the end.
For batteries at your own premises rather than a public charging business, see peak shaving and commercial battery storage. Investors weighing front-of-meter projects should read the grid-scale BESS guide.
Frequently asked questions
Why add a battery to an EV charging site?
To deliver more charging power than the grid connection alone allows. The battery refills slowly from the connection and discharges quickly during busy periods. A bigger connection or load management may be cheaper, so compare them.
Do I still need a DNO application with a battery?
Yes. The site needs a demand connection agreed with the DNO, and a battery that can export is generation under G98 or G99. A battery used to limit import still needs the DNO to approve the control scheme.
Is LEVI funding available for my charging hub?
The GOV.UK page we read describes LEVI as funding for local authorities in England, mainly for lower-power on-street charging for residents without off-street parking. We could not confirm its current status, so confirm any funding in writing before relying on it.
How big should the battery be?
It depends on the gap between charger demand and connection capacity, how long that gap lasts, and how much time the battery has to recharge. Use real session data and ask for the sizing assumptions in writing.
- ENA Distributed Generation Connection Guide, March 2025: G98/G99 thresholds, non-contestable reinforcement, interactive queues
- NGED: customer export limitation schemes: G100 limitation schemes for import or export
- GOV.UK: apply for LEVI funding: who LEVI is for (local authorities); page version read was dated 2023
- Planning practice guidance: renewable and low carbon energy: fire service engagement at 1 MWh or more
- Town and Country Planning Act 1990 s55: interior works are not development
- Reonic: commercial battery storage cost in the UK: overlapping per-kWh bands (secondary source, no figures used here)
- GOV.UK: Industrial Energy Transformation Fund: closure, no successor