Solar Battery Grants
Commercial

Using a Battery to Unlock a Constrained Grid Connection

On a constrained network, a behind-the-meter battery combined with an agreed import or export limit can sometimes let a site connect without waiting for reinforcement. Whether it works depends on the network operator's offer, not on the battery alone.

  • Independent: not a government site, not an installer
  • Every rule checked against official sources
  • Free, no obligation, we reply by email

Planning commercial battery storage?

Tell us about the site and we reply by email.

Free to useNot an installerWe reply by email

Updated 8 October 2026. Independent guide; not a government website and not an installer.

Short answer: a battery can help a site connect where the local network is tight, but only when the distribution network operator (DNO) agrees to a limited connection and the site can live inside that limit. The battery stores output or demand that would otherwise exceed the limit; an approved control scheme (ENA Engineering Recommendation G100) is what actually holds the site to the agreed figure. It is not a shortcut around the DNO process, and it is not a funding route. This page is general buyer education from an independent publisher, not engineering or legal advice.

What a battery does for a connection, and what it does not

The limitation scheme is the enabler

National Grid Electricity Distribution (NGED) describes a customer limitation scheme as an alternative for customers who want to increase generation or demand capacity and would otherwise face costly upstream reinforcement: the customer restricts the net export or import of their connection rather than wait for, or contribute to, that reinforcement. The scheme must bring current back to the agreed maximum import or export capacity, typically within 15 seconds, must fail safe, and its settings are protected so they cannot be changed without the DNO's written agreement. NGED says its approval is needed before installation, with an application form submitted alongside the generation application and a completion form within 28 days after the work.

Other DNOs run their own forms and processes, so treat NGED's page as an illustration and check your own operator.

Where the battery fits

In principle, a battery lets a site shift when it imports or exports so that the grid-facing figure stays under the limit while the site still uses its solar output, charging load or process demand. That is general reasoning, not a performance claim. How much it helps depends on the site's load shape, the size of the limit and the battery's power rating, none of which we can state in general.

Check first: ask the DNO, in writing, whether it will offer a limited or flexible connection for your site, and on what terms. Everything else follows from that answer.

G98 or G99: which route applies

The threshold is set per phase, not as a site total. G98 covers aggregate registered capacity of 16 A per phase or less (3.68 kW per phase), for fully type-tested equipment, with notification to the DNO no later than 28 days after commissioning. Above 16 A per phase you need G99, and the application goes in before equipment is installed (ENA Distributed Generation Connection Guide, March 2025). For an inverter, registered capacity is the lesser of the inverter rating and the energy source rating, so check how your installer has declared it.

G99 typeRegistered capacityConnection voltage
Type A0.8 kW to under 1 MWUnder 110 kV
Type B1 MW to under 10 MWUnder 110 kV
Type C10 MW to under 50 MWUnder 110 kV
Type D50 MW or moreAny capacity at 110 kV or above

Most commercial behind-the-meter batteries land in Type A. Commissioning differs by type: Type A needs the Installation Document within 28 days of commissioning, while Types B to D need at least 28 days' notice with energisation, interim and final operational notifications. The DNO may choose to witness tests, so do not assume it will or will not. Some DNOs publish fast-track routes for small installations that include export limits; check your operator's current page rather than relying on a summary.

Planning a commercial battery project? Tell us about the site and we reply by email.Send an enquiry

The DNO process in general terms

  1. Early enquiry or budget estimate. The ENA guide describes an indicative estimate based on a desktop study. It is subject to change and is not open for acceptance. Where the DNO does all the work, it gives 10 working days for this estimate.
  2. Formal application. Submitted before generation equipment is installed, with technical details of the equipment.
  3. Assessment and design. The DNO assesses network impact and, where needed, designs any extension or reinforcement.
  4. Connection offer. It sets out the works, any reinforcement, whether the connection is constrained or unconstrained, technical and commercial terms, costs and whether the DNO will witness commissioning.
  5. Acceptance. The acceptance window is set in the offer; the guide says typically 30 to 90 days and nearer 30 where applications are interactive.
  6. Build, commissioning and energisation.

Under Standard Licence Condition 15 the ENA guide lists quotation timescales of 30 working days for low voltage generation connections, 50 for high voltage and 3 months for extra high voltage, where you request only non-contestable services. These are regulatory quote times, not time to energise.

Why timelines are uncertain

  • Interactive applications: where offers use the same part of the network, they are queued by application date and an offer can depend on those ahead of you proceeding.
  • Reinforcement, when needed, is usually non-contestable work done by the DNO.
  • Accepted offers can be withdrawn if the DNO considers the project is not progressing.
  • DNOs may charge connection offer expenses (assessment and design fees) whether or not you accept, applied differently by each operator.

We have not quoted any single DNO's end-to-end timescale because we could not verify one from a primary source.

Reading the connection offer

Before signing, confirm: the maximum import and export capacity; whether the connection is constrained or unconstrained and what constraint conditions apply; the charges and what triggers each; the acceptance deadline; the commissioning and witness requirements; and what happens if you later want to raise the limit. Remember a G100 scheme's settings are locked against change without DNO agreement.

Planning and fire safety

Planning law in England treats works affecting only the interior of a building, or not materially affecting its external appearance, as not development. Outdoor containers or cabinets are operational development, and the permitted development rights for renewables do not include a battery storage class, so expect to ask the local planning authority. For systems of 1 MWh or more not associated with a dwelling, national planning guidance encourages applicants to engage the local fire and rescue service before applying. Listed buildings can need separate consent. Also tell your insurer early. See our commercial battery storage guide for the wider picture.

Funding reality

There is no grant for this use case that we can point to. The Industrial Energy Transformation Fund closed in July 2025 with no successor fund. The 0% VAT rate on battery installations applies to homes and relevant charitable buildings, not to general commercial premises, so budget for standard VAT. The Annual Investment Allowance gives 100% relief on up to £1m a year; above that, whether a battery is main-rate or special-rate plant is not settled, so ask your accountant. More in commercial battery funding.

Questions to ask installers and your DNO

  • Has the DNO confirmed in writing that a limited connection is available at this site?
  • Who submits the G99 and G100 applications, and who is responsible if the DNO rejects the control scheme?
  • Is the limit import, export or both, and what is the settings-change process?
  • What happens to the project if the offer lapses?
  • Which parts of the work are contestable?

Common mistakes

  • Ordering equipment before an offer is accepted.
  • Reading G98 as a site total rather than per phase.
  • Assuming the battery size sets the connection size; the agreed capacity does.
  • Ignoring the acceptance deadline.
  • Assuming a limit can be raised later without a new process.

Related guides: peak shaving, solar plus storage, and grid-scale BESS for a different business model.

Frequently asked questions

Can a battery get me a bigger grid connection?

Not by itself. A battery can help a site stay within an agreed import or export limit, but the DNO decides what connection capacity it will offer. A control scheme meeting ENA G100 is what holds the site to the figure, and the DNO usually has to approve it before installation.

What is the difference between G98 and G99?

G98 covers fully type-tested equipment up to 16 A per phase (3.68 kW per phase), with notification after commissioning. Above that you need G99, which means applying to the DNO before installing and waiting for a connection offer.

How long will the DNO take?

We could not verify a single end-to-end timescale. The ENA guide lists regulatory quotation times (for example 30 working days for low voltage generation, where you request only non-contestable work), but reinforcement, interactive queues and acceptance windows can add substantial time.

Is there a grant for grid-enabling batteries?

We found none. The Industrial Energy Transformation Fund closed in July 2025 with no successor fund, and the 0% VAT rate on batteries does not apply to general commercial premises. Capital allowances may help; ask your accountant.

Sources and how we checked
Check your eligibility
Check eligibility